Google has halted construction work on a multi-billion-euro artificial intelligence data centre in southern Belgium following a direct stop-work order from regional authorities.
The suspension took effect after inspectors in the Wallonia region observed active building operations at the 50-hectare site in Farciennes. Officials warned that ongoing structural work lacked valid legal permits.
Wallonia government spokesperson Nicolas Yernaux described the continuation of work as an unauthorised construction of a three-hectare facility. In response, Google confirmed it paused on-site activities while it seeks further administrative guidance.
Dispute Centres on River Sambre Water Cooling
The dispute stems from proposed modifications to the facility’s cooling system. Google’s local subsidiary, Crystal Computing, initially received planning permission based on an air-cooling design.
The technology company later submitted an amendment to combine two planned buildings into a single large centre. The revised filing also sought permission to cool equipment by drawing water from the nearby River Sambre.
Regional authorities initially approved the amendment in April. However, Walloon Spatial Planning Minister François Desquesnes revoked the permit in August following severe summer droughts, warning that climate pressures made prolonged river extraction unsustainable.
Environmental Backlash and Legal Scrutiny
Environmental groups and local residents campaigned against the water extraction plan. Campaigners highlighted that Google’s existing campus in Saint-Ghislain already consumes substantial municipal water reserves annually.
Satellite imagery and community reports revealed that structural building continued through the autumn despite the August cancellation. Approximately 300 on-site workers received orders to halt building activities after regional inspectors visited the grounds.
Google stated that it has operated in Belgium for more than 15 years and remains committed to following local regulations. The company has appealed the permit revocation before Belgium’s Council of State, with a formal court hearing scheduled for January.
The Broader Strain of Global AI Infrastructure
The Belgian standoff reflects a growing international debate over the physical resources required to run modern artificial intelligence models. Advanced chips generate massive heat, requiring vast electricity and cooling infrastructure.
Belgium currently hosts more than 50 data centres, while global facilities exceed 13,000 installations. As tech firms expand capacity across Europe, local communities increasingly challenge projects that threaten regional water basins and domestic power supplies.
Work on the Farciennes campus remains frozen until judicial reviews conclude. The outcome of the January court proceedings will determine whether Google must redesign its cooling architecture or face prolonged development delays.